Find what is truly unmovable in your schedule.
Each node shows four numbers: duration, Early Start, Early Finish and float. Nodes with float equal to zero form the critical path — highlighted in purple. The forward pass calculates the earliest each task can start and finish. The backward pass calculates the latest. Float is the gap between them. Drag the delay sliders to slip any task and watch the end date and critical path recalculate live.
The critical path changes during the project. A task that had float in week one may have none by week six because other delays consumed the buffer. PMs who calculate the critical path once at kickoff and never revisit it are managing a map that no longer matches the terrain. Recalculate it weekly during execution.